Why Isn't Planning Lead Time Based on Work Days?

Why Isn't Planning Lead Time Based on Work Days?

Release Date: 11/8/2018

Q - I saw your Knowledge Base article that explains how the planning lead time is based on calendar days:
But since you have a calendar file that indicates which days of the week the company is not open, why would the system move the planning date on to the next work day but not skip them in calculating the lead time? 

Example: We have a part with a 10-working-day lead time. The work order has a due date of 11/13 and the start date is 11/3.  Even though the calendar shows we are not working on certain days, it still counts those days as part of the lead time. This has caused issues for us in the past because I believe the same thing would happen even if I put holidays on the calendar.

AThe original developing of lead time logic was based on purchasing lead time, instead of manufacturing lead time.  In purchasing, especially for importers, if you have an 8 week lead time, most of that lead time is for shipping. The ship is sailing 7 days a week on the ocean. That is the reason why the lead time calculation is based on calendar days instead of working days.  The calendar file was added later on to avoid the scheduling date falling on weekend or holidays.

I understand your point. At this moment, we don’t have a method to support some item lead time based on calendar days and some other lead time based on work days. The result is the manufacturing items' lead time is also based on calendar days, similar to purchasing items.  That may cause the lead time for manufacturing items to be a few days off depending on the day of the week. So your strategy should be to give manufacturing item lead times a few days buffer to accommodate for this calculation issue.

EMK

    • Related Articles

    • What's the Difference Between Lead Time & Planning Lead Time?

      Q - We're in the process of using ATP and noticed on the Item File that there are two fields: one is Lead Time and the other is Planning Lead Time. We checked the documentation and it looks like Planning Lead Time is used in any MRP generation, but ...
    • Planning Lead Time by Calendar Days or Work Days?

      Q - When planning lead time in Elliott's Item Master table, is it by calendar days or working days? If it is by calendar day, then how do you prevent the planning lead time from falling on weekends and holidays? A - Elliott uses calendar days for ...
    • Customer Account Summary Inquiry Age Days Calculation Logic

      Release Date: 07/07/2021 Version: 8.5 Q - In A/R Customer Account Summary Inquiry, what is the logic on a partially paid invoice? See example below: In the above example, invoice number AXI990 was partially paid on 6/18/21. That is 49 days after the ...
    • BMWCTIME Bill of Material Work Center Time Clock

      Work Center Time Clock How to Access: Main Menu > Distribution > Bill of Material Processor > Maintenance > Work Center Time Clock Work Center Time Clock, 1st Stage This is the Time Clock Interface for a Work Center. It allows the operator to log ...
    • Can Item Lead Time Be Added to the Sales Desk Screen?

      Recently, we have been asked if there is there way to change the data in the QTY BO field to be Lead Time and to add Lead Time data on the Sales Desk screen. For some users, QTY BO is irrelevant on this screen. The answer is yes. You can replace "BO" ...