Why Isn't Planning Lead Time Based on Work Days?

Why Isn't Planning Lead Time Based on Work Days?

Release Date: 11/8/2018

Q - I saw your Knowledge Base article that explains how the planning lead time is based on calendar days:
But since you have a calendar file that indicates which days of the week the company is not open, why would the system move the planning date on to the next work day but not skip them in calculating the lead time? 

Example: We have a part with a 10-working-day lead time. The work order has a due date of 11/13 and the start date is 11/3.  Even though the calendar shows we are not working on certain days, it still counts those days as part of the lead time. This has caused issues for us in the past because I believe the same thing would happen even if I put holidays on the calendar.

AThe original developing of lead time logic was based on purchasing lead time, instead of manufacturing lead time.  In purchasing, especially for importers, if you have an 8 week lead time, most of that lead time is for shipping. The ship is sailing 7 days a week on the ocean. That is the reason why the lead time calculation is based on calendar days instead of working days.  The calendar file was added later on to avoid the scheduling date falling on weekend or holidays.

I understand your point. At this moment, we don’t have a method to support some item lead time based on calendar days and some other lead time based on work days. The result is the manufacturing items' lead time is also based on calendar days, similar to purchasing items.  That may cause the lead time for manufacturing items to be a few days off depending on the day of the week. So your strategy should be to give manufacturing item lead times a few days buffer to accommodate for this calculation issue.

EMK

    • Related Articles

    • What's the Difference Between Lead Time & Planning Lead Time?

      Q - We're in the process of using ATP and noticed on the Item File that there are two fields: one is Lead Time and the other is Planning Lead Time. We checked the documentation and it looks like Planning Lead Time is used in any MRP generation, but ...
    • Planning Lead Time by Calendar Days or Work Days?

      Q - When planning lead time in Elliott's Item Master table, is it by calendar days or working days? If it is by calendar day, then how do you prevent the planning lead time from falling on weekends and holidays? A - Elliott uses calendar days for ...
    • Feature - Synchronize Item Lead Time and Planning Lead Time

      Release Date: 7/31/24 Version: 8.5 and Above In Item Master File Maintenance, there are two lead time fields: Screen 2 - Field 45. Lead Time: This is a field used by the Inventory Management module like Reorder Advise Report and Usage Exception ...
    • Feature - Order Line Item Screen to Prompt WO Type, Buffer Days and Lead Time

      Release Date - 4/8/16 The purpose of the feature is to allow the user to specify what type of production order should be created when entering a line item in Customer Order Processing. Users will also be able to specify the buffer days and lead time. ...
    • Feature - Buyer's Desk Avg DOS Range and Lead Time Filter Criteria

      Release Date: 9/10/24 Revised Date: 10/14/24 Version: 8.5 and Above This feature added a new filter criteria to the two-location version of Buyer's Desk. The option "Starting/Ending Lead Time" allows the user to choose if items should be filtered ...