Q: We have a Work Order showing the status as "Partial Rprt (100% complete)" but is not posted to show Complete. The pending transaction shows "Error: Exists Other Unposted Transaction" on both the Edit List and Post Journal. In Review the Order Inquiry, all operations reported properly. Can we force the system to complete the order?

A: Yes. The system provides an "Override Post for Exception" way to accomplish the order.   
1. You should be a high-level-permission operator.

2. At Production Transaction change mode, go to field # 5 "QTY Complete." You will see the
option  F5 (Override Post Excp). Hit F5 to override it.




3. 
 After that, press F5. Then, when you see the message below “Are You Sure To Proceed,” answer “Y.”

4. 
 Answer “Y’ to confirm that you want to “Override Posting Exception.”





5. 
After posting, you will see that the order status is marked “Complete.”


EMK







    • Related Articles

    • Feature - Update Newly Received for Plus Work Order Copied from COP

      Released Date: 02/20/2025 Version: 8.5 & Up In Elliott BOMP Plus Work Order, when a production is completed and posted, it will not update the Newly Received (CPITMREC) database if the plus work order was originally copied from the COP sales order. ...
    • AP0202 Accounts Payable Transaction Processing

      Processing A/P Transaction Processing Advanced Features The A/P Modules includes many features and functions, not applicable to all business, which we let you Pick & Choose to enhance your functionality and processing needs. These are detailed in the ...
    • AP08S2 Accounts Payable Post A/P Checks

      Post A/P Checks Application Overview The Post A/P Checks application automatically updates the amount that your business has paid to a given vendor. It will post the checks that have been printed in Print Checks application. When performing a ...
    • Work Order Plus Management Manual 9

      WIP Variance Report Application Overview The WIP Variance Report prints out the WIP Variance Amount, Standard Cost Variance Amount and Scrap Amount for each production transaction. The transactions are posted through the Post Production Transactions ...
    • I Am Not Able to Copy Product Structure in Material Work Order

      Release Date: 01/30/2025 Version: 8.2 & Up Q - In this following Knowledge Base article: https://support.elliott.com/knowledgebase/articles/1162930-feature-material-work-order-copy-product-structu it states "This feature allows a user to copy the ...