Feature - Order Line Item Screen to Prompt WO Type, Buffer Days and Lead Time

Feature - Order Line Item Screen to Prompt WO Type, Buffer Days and Lead Time

Release Date - 4/8/16

The purpose of the feature is to allow the user to specify what type of production order should be created when entering a line item in Customer Order Processing. Users will also be able to specify the buffer days and lead time. This feature is enabled in Global Setup -> Dist -> BOMP Global Control at field 20. Copy Mfg Item From COP For This Vendor Only?

If the user enters a value that’s not blank in field 20, then a pop-up window will ask the user:

             Enter production info for line item in popup window?

The default value is “N.” If the user answers Yes, a window will pop up and prompt the user for more information about the production order.


This window will pop up if the user enters the matching vendor in field 12, Vendor 12.

For Work Order Type, the user can enter:

Blank = Default
O = Legacy Work Order
M = Material Work Order
P = Plus Work Order

Blank is the default value. If you leave this field blank, then the Buffer Days and Production Lead Time will be skipped, which means all three fields are not used. 

For Buffer Days, the default value will come from BOMP Global Control, field “10. Buffer Days to Use When Copy COP to BOMP WO?” The user can override this value. The expected date is calculated using this value. Once the buffer days are entered, the user can manually enter the expected date. If the user overrides the calculated date, the buffer days is recalculated and updated on the screen.

For Production Lead Time, the default value will come from Item Master planning lead time. The user can override it. The expected date is calculated using this value.  Once the production lead time days are entered, the user can manually enter the expected date. If the user overrides the calculated date, the production lead time days is recalculated and updated on the screen.

The above values will be used in the following areas:

(1)    BOMP -> Processing -> Copy COP Orders Into BOMP.  On that screen, the field “5. Copy to WO Type” value will be compared against the value that was entered in order entry. If it  matches, the production order will be created. If the work order type specified on the order line does not match, the line item will be skipped and no production work order will be generated.

(2)    BOMP -> Processing -> Production Order Entry. You may be in either Legacy, Material or Plus Work Order. In the “2. Item No” field, you can press F3/F4 to copy from COP by Order#/Item#. If the work order type entered on the COP order does not match the work order type application you are in, the system will not display the item in the list to be copied.

(3)    IM -> Util-Setup -> ATP Regen & Processing -> ATP Processing. You may convert an “O” type of record to work order.  The system will respect the value in LINE-ITEM-BOMP-ORDER-TYPE when creating the work order type specified on the order line item.

In addition, we need to change the following areas in Order Entry to support these three new fields:

Copy Order – The value entered will be copied to the new order created. 
Consolidate Order – The value entered will be consolidated on the new order.
Blank Order - The value entered will be on the releases created.
Opposite ATP - When the opposite ATP records are generated for feature items, the opposite ATP record will calculate the transaction date using the buffer days and lead time entered on the line item, if applicable.

Once the production work order for the line item has been created in the Bill Of Material module, the screen will display the work order number and the actual start and due dates. Once the production work order has been created, the values on the Order Line Item cannot be changed.


Modified Programs: NSCTLFIL.FD, NSCTLFIL.W30, NSCTLINI, NSCTLMN3, BMCOPGEN.WS, BMCOPGEN.PL, IM0405.PL, BM1701, BM1702, BM1703, BM26P1, BM26P1A, BMRTGMNT, CP0102, CP0111, CP0114, CP0115BM, IMATPGEN, SYINVAL2, SYINVAL3, SYINVALO

CLS




    • Related Articles

    • Feature - Synchronize Item Lead Time and Planning Lead Time

      Release Date: 7/31/24 Version: 8.5 and Above In Item Master File Maintenance, there are two lead time fields: Screen 2 - Field 45. Lead Time: This is a field used by the Inventory Management module like Reorder Advise Report and Usage Exception ...
    • What's the Difference Between Lead Time & Planning Lead Time?

      Q - We're in the process of using ATP and noticed on the Item File that there are two fields: one is Lead Time and the other is Planning Lead Time. We checked the documentation and it looks like Planning Lead Time is used in any MRP generation, but ...
    • Why Isn't Planning Lead Time Based on Work Days?

      Release Date: 11/8/2018 Q - I saw your Knowledge Base article that explains how the planning lead time is based on calendar days: https://support.netcellent.com/portal/en/kb/articles/planning-lead-time-by-calendar-days-or-work-days But since you have ...
    • Feature - Staging Slip Orders with WO Line Item Only Flag

      Release Date: 04/20/2021 Version: 8.5 In COP -> Processing -> Print Pick/Pack Ticket & Lbls -> Print -> Staging Slip, when the user chooses Order Type = "S" (Sales Order), and presses F5=Enter Range, the flag "Orders with WO Line Item Only?" is used ...
    • Feature - Print Pick Ticket to Create Transfer Batch to Use Ship Date - Buffer Days