Feature - Export BOMP Material WO Production Scheduled Report to CSV

Feature - Export BOMP Material WO Production Scheduled Report to CSV


Release Date: 11/10/2022

Version: 8.5 and Up

A new feature has been added to allow Export of the  BOMP Material WO Production Scheduled Report data to a CSV file.  There are two new setup fields in Global Setup / Dist / BOMP global control / Screen 7 that affect this new feature.  First, field 3 allows control over which notes will be on the CSV, by note type entered.  Leaving this field blank will cause there to be no note information on the CSV file.  Second, field 4 allows setup of a password value that will be matched to an entered value when tabbing of field "19. Export to CSV" in the Production Schedule report screen.



When field "9. Work Order Type" is "M," field "19. Export to CSV?" is now available.


If "Y" is entered in field 19, and a password is set up in Global Setup, a Password ? window will appear.  If an incorrect password is entered, control will return to field 19.



If a correct password is entered, or a password has not been entered in Global Setup, the "Export Path and File Name" window will appear.




The CSV will have the following columns:
  • WO#
  • Loc
  • Item#
  • Desc
  • Desc2
  • Cat
  • Due
  • Start
  • UOM
  • QtyOrd
  • Complete
  • Balance
  • OrdSts
  • JobNo
  • Custom
  • Note1 thru Note10 (if Note Type is set up in Global Setup) 
Here is a sample of the CSV file:



Modified programs:
NSCTLFIL.FD, NSCTLFIL.W38, NSCTLINI, NSCTLMN3, BM25S1, BM25P3

DLM


    • Related Articles

    • BMWORSCN Bill of Material Production History Report for WO+

      Production History Report for WO+ Application Overview The Production Transaction History Report prints production transactions reported for selected production orders. It prints the number of items reported in each transaction and the total amount ...
    • BMRTGMNU Bill of Material Production Routing

      Production Routing Run Instructions Select Production Routing File from the pull down BOMP Maintenance window. The following screen will be displayed: Routing Maintenance Screen Production Routing describes how each parent item is manufactured, step ...
    • BM1800 Bill of Material Production Transaction Processing

      BM1800 Bill of Material Production Transaction Processing ← Bill of Material / Work Order Plus Production Transaction Processing Application Overview The Production Transaction Processing application allows for reporting progress made toward ...
    • BMSCHSCN Bill of Material Production Schedule Report

      Production Schedule Report Application Overview The Production Schedule Report prints a list of items scheduled to be produced. These items are entered through orders in the Production Order Entry application, copied from Customer Order Processing, ...
    • BM1700 Bill of Material Production Order Entry

      BM1700 Bill of Material Production Order Entry ← Bill of Material / Work Order Plus Processing Production Order Entry Application Overview The Production Order Entry application allows the entry of production orders. These orders may be later ...