How to Access:
Main Menu > Distribution > Bill of Material Processor > Maintenance > Work Center Time Clock
Work Center Time Clock, 1st Stage
This is the Time Clock Interface for a Work Center. It allows the operator to log into a work center and the labor will be shared among any work orders currently active in this work center. This type of operator does not report about a work order or completed quantity, but only needs to clock in or out from one work center to another. This is suitable for assembly line workers or CNC machine operators.
This interface is simpler than Work Order Production and only needs two stages.
An operator must first select a work center for this interface. The F7 Key can be pressed to search available work centers. The work center field may be left blank if the operator would like to start an activity for a special operation. This can be used at the beginning of a day when no job has been assigned to the operator.
Work Center Time Clock, 2nd Stage
This stage will display all operators who are currently in this work center. The system will show basic statistics about this work center under the work center ID.
The system will prompt for an Operator ID in this stage. Like the first stage of Work Order Production, the operator can scan a barcoded badge or type the ID and password manually. In manual mode, the operator can use the Up and Down Arrow keys to select one operator. The system will select the highlighted Operator ID, but the password will still need to be entered.
After the operator ID and password have been entered, the behavior is fairly simple:
Work Center Time Clock, 2nd Stage, List of Special Operation
If a Work Center ID was not entered, for Special Operation Mode, the system will provide a list of special operations to choose from each time the operator logs in.
If an operator needs to change work centers, it is not necessary to clock-out from the current work center. You can simply walk to the new work center and clock into the computer at that work center. The system will automatically clock the operator out from the previous work center. If the production department does not have multiple computers, you can press the Escape key and enter a new work center ID to clock in.